Certified Data Management Professional – Fundamentals (CDMP) — Question 66
Which of the following is NOT a stage in the Shewhart / Deming Cycle that drives the data quality improvement lifecycle?
Answer options
- A. Do
- B. Act
- C. Investigate
- D. Check
- E. Plan
Correct answer: C
Explanation
The Shewhart / Deming Cycle consists of the stages Plan, Do, Check, and Act, which are essential for continuous improvement. 'Investigate' is not one of these defined stages, making option C the correct answer. Options A, B, D, and E are all integral parts of the cycle.