Blue Prism Certified Developer (AD01) — Question 99

According to Blue Prism best practice which of the following information would be appropriate to store in a Work Queue tag? (select 3 responses)

Answer options

Correct answer: A, C, E

Explanation

The correct answers A, C, and E pertain to identifying the type of work, its source, and the type of process scenario, which are vital for categorizing and managing work effectively in Blue Prism. Options B, D, and F are not aligned with best practices for Work Queue tags, as they focus on timestamps, client identification, and exception details rather than the work type and its context.