Registered Communications Distribution Designer (RCDD) — Question 1
An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?
Answer options
- A. Reject the submittal after verifying compliance with applicable standards.
- B. Approve the submittal after asking about additional compensating warranty offerings.
- C. Approve the submittal after verifying code compliance.
- D. Approve the submittal after verifying all significant features of the originally specified product are met.
Correct answer: C
Explanation
The correct action is to approve the submittal after verifying code compliance because this ensures that the product meets legal and safety standards. While verifying significant features is important, code compliance takes precedence to ensure the safety and legality of the installation. Rejecting the submittal or approving it based on warranty offerings does not address the immediate need for compliance with regulations.