Atlassian Certified Professional – Jira Service Management Administrator (ACP-600) — Question 47
Which two statements are true about priorities in Jira? (Choose two.)
Answer options
- A. Priorities can only be reordered. Existing priorities cannot be edited.
- B. Jira administrators can set up individual priority schemes for each project.
- C. Project administrators can always update priorities in their projects.
- D. Project administrators can only update their project's priorities if the Extended project administration is enabled.
- E. Jira administrators can define global priorities.
Correct answer: A, B
Explanation
Answer B is correct because Jira administrators indeed can create unique priority schemes for every project. Answer A is also correct, as priorities can be reordered but not edited. The other options are incorrect because project administrators do not always have the authority to change priorities, and modifying priorities may depend on specific settings like Extended project administration.