Atlassian Certified in Managing Jira Projects for Cloud (ACP-100) — Question 3

Three team members have left the company and their issues need to be re-assigned to various -users.
All of their issues are in the Marketing project which uses the Default Notification Scheme. The scheme has never been updated.
How do you inform the new assignees about their re-assigned issues?

Answer options

Correct answer: D

Explanation

The correct answer is D because performing bulk operations allows for the re-assignment of issues while simultaneously notifying the new assignees in accordance with the Default Notification Scheme. Options A, B, C, and E do not ensure that notifications are sent to all new assignees effectively or do not utilize the existing notification mechanism.