ASQ Certified Quality Engineer (CQE) — Question 46
A purchase order for subassemblies classified as critical must include a review by
I. Quality engineering.
II. The procurement department.
III. Design engineering.
Answer options
- A. III only
- B. I and III only
- C. II and III only
- D. I, II and III
Correct answer: D
Explanation
The correct answer is D because all three departments—Quality engineering, the procurement department, and Design engineering—play essential roles in ensuring that critical subassemblies meet quality and design standards. Options A, B, and C are incorrect as they exclude one or more necessary reviews that are vital for the purchase order process.