ASQ Certified Manager of Quality / Organizational Excellence (CMQ/OE) — Question 35
Which of the following levels of the work breakdown structure (WBS) includes an explanation of the purpose of the project?
Answer options
- A. Project
- B. Phase
- C. Activity
- D. Task
Correct answer: D
Explanation
The correct answer is D, as the Task level in the WBS provides detailed descriptions, including the purpose of the project. The Project level offers a broad overview, while Phase and Activity levels focus on segments and specific actions, not the overarching purpose.