Appian Associate Developer (ACD100) — Question 42
Who is responsible for estimating the level of effort for Product Backlog items?
Answer options
- A. Product Owner
- B. Testers
- C. Developers
- D. Scrum Master
Correct answer: C
Explanation
The Developers are responsible for estimating the level of effort required for Product Backlog items, as they have the technical expertise to determine effort based on their understanding of the tasks. The Product Owner focuses on prioritizing the backlog, while Testers and the Scrum Master have different roles that do not involve estimation.