APICS Certified Supply Chain Professional (CSCP) — Question 9
After identifying the potential causes for delays in communicating demand information up the supply chain, the trading partners should take which of the following actions?
Answer options
- A. Implement a higher-speed data communications network.
- B. Change procedures so data is communicated more frequently.
- C. Identify the root causes for the delays.
- D. Map and analyze the value stream.
Correct answer: C
Explanation
The correct action is to identify the root causes for the delays, as understanding these causes is essential for addressing the issue effectively. While implementing a faster network, changing procedures, or mapping the value stream might help, they do not directly address the fundamental reasons for the delays.