APICS Certified Supply Chain Professional (CSCP) — Question 317

A master scheduler receives a new order with a due date inside the demand time fence (DTF). The best response is to:

Answer options

Correct answer: C

Explanation

The correct answer is C because the master scheduler needs to evaluate how the new order affects existing orders before making a decision. Options A and D do not consider the potential impact on current commitments, while B prematurely rejects the order without assessing its implications.