APICS Certified Supply Chain Professional (CSCP) — Question 299
The strategy to implement supplier relationship management has been developed. The most appropriate next step is to:
Answer options
- A. develop criteria for prospective partners.
- B. develop policies for alliances.
- C. select initial partners.
- D. conduct a pilot implementation.
Correct answer: A
Explanation
The correct answer is A because developing criteria for prospective partners is essential to ensure that the right partners are selected based on strategic alignment. Options B, C, and D are not the immediate next steps; policies and alliances require criteria to be established first, and selecting partners or conducting a pilot comes after criteria development.