APICS Certified Supply Chain Professional (CSCP) — Question 275
Advanced planning and scheduling (APS) generates optimal solutions primarily through the use of:
Answer options
- A. linkages to the master production schedule (MPS).
- B. linear programming and related mathematical models.
- C. real-time demand and inventory data.
- D. process flow analysis.
Correct answer: A
Explanation
The correct answer is A because APS uses linkages to the master production schedule (MPS) to align production plans with demand. Options B, C, and D are important aspects of planning but do not primarily drive the optimal solutions in APS as effectively as the MPS does.