APICS Certified Supply Chain Professional (CSCP) — Question 275

Advanced planning and scheduling (APS) generates optimal solutions primarily through the use of:

Answer options

Correct answer: A

Explanation

The correct answer is A because APS uses linkages to the master production schedule (MPS) to align production plans with demand. Options B, C, and D are important aspects of planning but do not primarily drive the optimal solutions in APS as effectively as the MPS does.