APICS Certified Supply Chain Professional (CSCP) — Question 26

The four risks of supply chain risk management are supply, demand:

Answer options

Correct answer: C

Explanation

The correct answer is C, as the four risks include supply, demand, process, and environmental factors. Options A and B do not accurately represent the recognized risks in supply chain risk management, while option D incorrectly replaces process with value.