APICS Certified Supply Chain Professional (CSCP) — Question 245
Which of the following events would initiate an update of a manufacturing site business continuity plan?
Answer options
- A. A major renovation and asset consolidation program
- B. A power outage lasting more than 48 hours
- C. A country's upcoming political election
- D. A one-week supply interruption from a vendor
Correct answer: A
Explanation
Option A is correct because significant renovations and asset consolidations can affect operations and require an update to the continuity plan. The other options, while impactful, do not necessitate a comprehensive revision of the plan as they are more temporary or specific issues rather than long-term structural changes.