APICS Certified Supply Chain Professional (CSCP) — Question 14
In an assemble-to-order manufacturing environment, the master production schedule is typically the schedule of:
Answer options
- A. resources.
- B. customer orders.
- C. components and subassemblies.
- D. the final assembly.
Correct answer: C
Explanation
The master production schedule in an assemble-to-order environment primarily details the components and subassemblies needed for production, which is essential for meeting customer demands. Options A and B do not directly relate to the specifics of the components required for assembly, while option D focuses only on the final stage of production rather than the entire assembly process.