APICS Certified in Production and Inventory Management (CPIM) — Question 5
A main objective of material requirements planning (MRP) is to determine:
Answer options
- A. finished goods production schedules.
- B. dependent demand schedules.
- C. inventory levels for finished goods.
- D. inventory levels for components.
Correct answer: D
Explanation
The correct answer is D because MRP focuses on ensuring that the necessary components are available for production, which involves calculating inventory levels for those components. Options A and C pertain to finished goods, which are not the main focus of MRP, while option B addresses dependent demand but does not specify inventory levels.