In an assemble-to-order production environment, the master production schedule contains:
Answer options
- A. standard items.
- B. finished items.
- C. raw materials.
- D. subassemblies.
Correct answer: D
Explanation
The correct answer is D, as the master production schedule in an assemble-to-order environment focuses on subassemblies that need to be completed to fulfill customer orders. Options A, B, and C are incorrect because they refer to items that are either standard, finished, or raw materials, which are not the primary focus of the schedule in this specific production strategy.