APICS Certified in Logistics, Transportation and Distribution (CLTD) — Question 84
Given the data below, what would be the new reorder point (ROP) if the lead time were reduced by 20%?
Daily demand = 20 units -
Reorder lead time = 10 days -
Safety stock = 15 units
Answer options
- A. 160 units
- B. 175 units
- C. 195 units
- D. 215 units
Correct answer: B
Explanation
To calculate the new ROP, first determine the new lead time by reducing the original lead time of 10 days by 20%, resulting in an effective lead time of 8 days. Then, calculate the ROP using the formula: ROP = (Daily demand * Lead time) + Safety stock, which gives (20 units * 8 days) + 15 units = 175 units. The other options do not reflect this calculation.