APICS Certified in Logistics, Transportation and Distribution (CLTD) — Question 53
A company receives automobile parts from global manufactures into its distribution center before redeploying the parts to local retail outlets.
Which of the following documents can be used to proactively plan for the redeployment of the parts?
Answer options
- A. Bill of lading (B\L)
- B. Advance ship notice (ASN)
- C. Routing guide
- D. Shipment manifest
Correct answer: A
Explanation
The Bill of Lading (B/L) serves as a contract between the carrier and the shipper, detailing the shipment and facilitating the planned movement of goods. The Advance Ship Notice (ASN) provides information about upcoming shipments but is not primarily used for proactive planning. A Routing Guide outlines preferred shipping routes but doesn't directly assist in the planning of redeployment like a B/L does. The Shipment Manifest lists all items in a shipment but lacks the contractual and planning aspects provided by a B/L.