A company is evaluating options to migrate its on-premises SAP ERP Central Component (SAP ECC) EHP 8 system to AWS. The company does not want to make any changes to the SAP versions or database versions. The system runs on SUSE Linux Enterprise Server and SAP HANA 2.0 SPS 05. The existing on-premises system has a 1 TB database.

The company has 1 Gbps or internet bandwidth available for the migration. The company must complete the migration with the least possible downtime and disruption to business.

Which solution will meet these requirements?

Answer options

Correct answer: B

Explanation

Option B is optimal as it allows for replication and minimizes downtime, ensuring the business can switch to the AWS environment with minimal disruption. Other options involve longer processes like full backups and restores, which can lead to increased downtime and complexity in migration, making them less suitable for the company's requirements.