AWS Certified SAP on AWS – Specialty (PAS-C01) — Question 117

A company wants to migrate its SAP S/4HANA infrastructure to AWS. The infrastructure includes production, pre-production, test, and development environments. The pre-production environment is an identical copy of the production environment.

The production system must comply with a new policy that requires the landscape to be able to fail over to a secondary AWS Region. The required RPO is 5 minutes. The required RTO is 4 hours. The estimated SAP HANA database size is 6 TB.

Which solution will meet these requirements MOST cost-effectively?

Answer options

Correct answer: A

Explanation

Answer A is the most cost-effective solution as it utilizes the pre-production environment for disaster recovery, minimizing additional resource requirements. Options B and C involve creating larger DR environments that may incur higher costs, while option D does not meet the requirement for a secondary AWS Region for failover.