AWS Certified Advanced Networking – Specialty (ANS-C00) — Question 95
Your company has a highly-available Direct Connect solution that utilizes two datacenters. Each datacenter was initially configured with one four-connection LAG and one standard DX connection. How many LOA documents have been requested and completed for this configuration?
Answer options
- A. 1
- B. 4
- C. 2
- D. 10
Correct answer: D
Explanation
The correct answer is D because each of the four connections in the LAG requires its own LOA, plus one additional LOA for each standard DX connection, resulting in a total of 10 LOAs (4 for the LAG and 2 for the standard connections). Options A, B, and C do not account for the total number of required LOAs based on the connections described.