CFE – Financial Transactions and Fraud Schemes — Question 13
Which of the following is the MOST ACCURATE statement about the phases of procurements involving open and free competition?
Answer options
- A. In the post-award and administration phase, the procuring entity identifies its needs and develops the criteria used to award the contract.
- B. In the solicitation phase, prospective contractors prepare and submit their bids.
- C. In the bid evaluation and award phase, the procuring entity fulfills its duties through the performance of its contractual obligations.
- D. In the presolicitation phase, the procuring entity issues the solicitation document.
Correct answer: D
Explanation
The correct answer is D because the presolicitation phase is specifically when the procuring entity issues the solicitation document to invite bids. Option A incorrectly defines the post-award phase, while option B mischaracterizes the solicitation phase as one where bids are prepared rather than issued. Option C inaccurately describes the bid evaluation phase by focusing on contractual obligations instead of the evaluation process itself.